Lincoln Square's Rec Center Is Coming Down. Here's What Chinatown Families Can Still Use, and for How Long.

  • November 12, 2026

Walk the block bounded by 10th, 11th, Harrison and Alice this week and you'll see fencing around half of it. On the fence, Friends of Lincoln Square Park has hung bilingual signs showing renderings of the building that will replace the old one. The AC Transit stop at 11th and Harrison has moved mid-block, closer to Alice. Behind the fence, the nearly 50-year-old Lincoln Square Recreation Center is being torn down. The City's park page says demolition began Wednesday, November 4.

For Chinatown families, fall 2027 is the date to plan around. Under the City's Phase 1 plan, half the park, including both playgrounds, stays open from July 2026 to fall 2027. After that, Phase 2 closes the entire block. So for about the next year, Lincoln Square runs as two places at once. The outdoor half is still on the block, and the indoor programs are spread across borrowed rooms a few blocks away.

The open side of the fence

The City's Lincoln Square park page lists what Phase 1 keeps open:

  • Both playgrounds, including the tot lot for kids 5 and under
  • The Alice Street alley, which got new landscaping at the Friends' Earth Day event
  • The outdoor gym
  • The soccer field and the four-square courts
  • The outdoor stage
  • A reduced set of basketball hoops

The brick clubhouse at 261 11th Street, entered from inside the park, is where Friends of Lincoln Square Park sends people for real-time program updates. Its October construction and park update says program staff will keep watching the outdoor areas whenever they can. That update also covers evenings. Crews have started switching the park's lighting from its existing power to temporary construction power, and parts of the park may not be fully lit after dark during the changeover. A volunteer audit found five streetlights out in and right around the park. Those lights sit outside the project area, and the Friends group is following up with the City's streetlight division.

Neighbors also asked for wider sidewalks around the work zone. After community concerns, S.J. Amoroso Construction reconfigured the perimeter fencing so the sidewalks are wider and safer.

Where the indoor half went

The old building was small for what it carried. The City describes the 7,500-square-foot center, built in the late 1970s, as Oakland's most-used recreation center. Center director Gilbert Gong told Oaklandside that 2,000 people a day came through its doors. Seniors used it for tai chi, line dancing and table tennis, and kids from Lincoln Elementary next door used it for after-school programs and basketball. Gong also said the building had only four bathroom stalls.

That load has now been split up. Here is where each piece stood as of the Friends group's late-October update:

Program Where it is now Address
Youth programs, including Lincoln Explorers Malonga Casquelourd Center for the Arts 1428 Alice Street
Senior programming Oakland Asian Cultural Center 388 Ninth Street, 2nd floor of Pacific Renaissance Plaza
Gym-based sports Temporarily suspended, not yet relocated None
Youth outdoor time Snow Park, by Lake Merritt None

Malonga is three blocks north on Alice Street. The building is already busy, since the Malonga Arts Collective describes it as home to ten nonprofit arts groups plus individual teaching artists. According to the Friends update, the space still needs more work before Lincoln Explorers can use every area available to them. Gong told Oaklandside in August that he was still looking for space for some programs. Some longtime users, many of them elders or immigrants living in Chinatown, had told him they worried about losing access to these resources during the long closure.

Of everything in the table, gym sports are the clearest gap. Gong told Oaklandside that the outdoor basketball courts would close during construction and that one group of 35-plus adult players had recently gathered. "The guys have come to use this as their bonding space," he said. The City also calls Lincoln Square the training home of its citywide volleyball program. For now, the indoor gym that supported that program has no replacement.

The demolition calendar, as it stands

Demolition was first signed for October 7. It slipped to November 4 while the City and contractor worked with EBMUD and PG&E to shut off gas, water and electricity and finish permits. Cutting the utilities was the last step before the building could come down.

On publish day, here is the posted schedule:

  1. Through November 20: structural demolition, scheduled to wrap by that date.
  2. Weekdays, daytime: the park page gives 8 a.m. to 4 p.m. for heavy demolition inside the fenced boundary, and the City's demolition update, revised October 30, gives 8 a.m. to 5 p.m. for building demolition. Expect noise, dust and debris in that window.
  3. After November 20: site clearing and tree removal inside the fenced area.
  4. Throughout: construction vehicles come and go through 11th Street, with temporary traffic control and marked pedestrian routes.

To keep dust inside the site, the contractor is watering down materials and keeping a dust screen along the fence. The City posts schedule changes on its demolition update page. Construction questions go to Amber Kennedy at 510-238-2682. Questions about park operations go to Quincy Williams at 510-424-3371. Parking on 10th and 11th streets may be affected from time to time, and the City says to watch for posted notices.

Why fall 2027 is the date to circle

On the City's project page, the project runs in two phases. Phase 2 demolition starts in fall 2027, and the next round of construction follows right after. At that point the playgrounds, the Alice Street alley, the soccer field and the outdoor gym all close along with everything else.

That full closure matters because of a line on the same City page. Lincoln Square was the only public park and recreation center in Chinatown and Downtown Oakland with park staff, public restrooms and programming on site. Until fall 2027, the staffed outdoor half keeps a piece of that going on the block. Once Phase 2 starts, the nearest equivalent is wherever programs have landed by then, and for youth, Snow Park by the lake is already in that rotation.

The estimates for reopening vary. The City puts completion at winter 2027/2028. Oaklandside's groundbreaking coverage and the Friends of Lincoln Square Park FAQ both give summer 2028.

The community has also lost a few gatherings to the schedule already. Lincoln Summer Nights was scheduled for the second Thursday of each month from May through October, 5 to 8 p.m. The final date, October 8, was canceled because of construction.

What gets built in the gap

The new building is designed to more than make up for the disruption. It's a two-story, roughly 22,000-square-foot recreation and resilience center, about three times the size of the 7,500-square-foot building it replaces. Oaklandside reports the gym will be twice as large. The City lists multipurpose classrooms, a multipurpose room with a stage, a central kitchen, indoor gym space, a roof garden, and solar panels with battery backup. The building is targeting LEED Gold and will be the City's first resiliency center.

According to Oaklandside, the "resilience" part grew out of workshops the Asian Pacific Environmental Network held with its mostly senior Chinatown members. Some asked for refrigeration so their medication would survive power outages, and many asked for cleaner air during wildfire smoke. The design responds with MERV 13 air filtration, showers, phone charging, and enough battery storage for the building to run on its own for a few days during a long outage. Twenty new trees are planned for shade.

Funding was assembled over years. The City put in $1.7 million in FY20 to start planning. With Friends of Lincoln Square Park and APEN, it then won an $8.5 million Proposition 68 grant and a $9.25 million California Department of Food and Agriculture grant, and federal HUD funds and local Measure KK and Measure U money followed. Shah Kawasaki Architects, an Oakland firm, designed the building.

Gong first played at Lincoln Square as a child after Chinese school, and he summed up the project at the July 30 groundbreaking, as Oaklandside reported:

"For me, it's a full circle. The park cared for me and took care of me as a child, and I'm trying to reciprocate that here as best as possible for as many people as possible."

His work at the park is also the subject of a short documentary, Gilbert Gong: Heart of Lincoln Square. It had its Oakland debut at the Grand Lake Theater on October 7, with a performance by the Lincoln Explorers Lion Dancers. Funding for the programs that keep running during construction is still being raised. Through its Lincoln Legacy Campaign, the Friends group aims to raise $2 million over three years, covering programming during construction and a lasting endowment for the new center.

At Hope Broderick & Co, we follow projects like Lincoln Square because they change how a block works day to day, long before a ribbon is cut. If you live near the park and are planning updates to your own home during this construction stretch, we're happy to help you map out a timeline around the work. Start your home transformation with us.